MX/DDC-100 Field Unit Installation and Maintenance FCD LMENIM2329-01 – 03/11
64
Contractor Tasks
Deliverable From To Comments
Specifications Engineer Contractor Complete P&IDs for site
Schedule Engineer Contractor Time line complete w/milestones
Project
Responsibilities
Engineer Contractor Define which supplier is responsible for each portion of project
P&ID Engineer Contractor
Detailed layout and instructions for building site. Information should include
actuator tag names, required data points from actuator, field unit, and field wiring
Site Electrical
and electronics
Engineer Contractor
Detail site electrical requirements, cable type, layout, and locations. Voltages
available for equipment
Loop Drawings Engineer Contractor
Detail cable routings from Host to each field device. This defines how the network
cable is to run throughout the facility
Schedule Contractor Limitorque
Provide material delivery dates for hardware. Schedule Flowserve Limitorque
Controls Service Technician for actuator commissioning (when requested
according to purchase order)
Hardware
Limitorque,
OEM
Contractor
Provide Motor-Operated Valves, RS-232/485 converters (if supplied), valves,
mounting adapters, etc.
Manuals Limitorque Contractor
Product Bulletins for Actuators:
•LMAIM4019Direct-to-HostProgrammingGuide
•LMAIM1329AccutronixInstallationandOperationforMX-DDCFieldUnit
•LMAIM4029DDC-100UECFieldUnit(Modbus)InstallationandOperation
Manual
•LMAIM4030DDC-100UECFieldUnitInstallationandCommissioningManual
•LMAIM4022DDC-100UECFieldUnitWiringandStartupGuidelines
•ModiconModbusProtocolReferenceGuidePI-MODBUS-300Rev.G(available
from Modicon)
Operational
System
S.I. Contractor Develop and test programming for DCS system
Documents S.I. Contractor
Documentation of program operational characteristics, equipment used, and
Operation and Maintenance Manuals for equipment
Schedule Contractor S.I.
Provide delivery dates for commissioning control system. Include dates for testing,
documentation, and turnover to site personnel
Hardware
for system
development
Contractor S.I. Hardware may include: DDC-100 Field Units, RS-232/485 converters
Actuator Contractor S.I. Availability of DDC-100 Field Unit for testing developed application software
Site Preparation Contractor S.I. Complete actuator or field unit installation. Provide actual (as installed)
Site Preparation Contractor Limitorque
Install specified equipment, cables for power and network communication. Verify
all network and power cables are properly routed, terminated, and documented
prior to commissioning of DDC-100 Network. The contractor should provide
detail on network routing from Host system to each field unit. Verify all field units
are properly grounded
Field Unit
Startup
Limitorque Contractor According to purchase order requirements, when scheduled