3. Cut away the foil shield. Strip the insulation from the conductors approximately 0.4 inch (1 cm)
as shown in Figure 2.16.
Figure 2.16 – Stripping Conductors
4. Apply heat-shrink tubing to insulate the braided shield and to provide stress relief to the cable as
shown in Figure 2.17.
Figure 2.17 – Applying Heat-Shrink Tubing
a
CAUTION: Do not melt the insulation during the application of heat-shrink tubing.
5. Install ring tongue connectors as shown in Figure 2.18.
NOTE: Flowserve recommends the use of Thomas and Betts #RZ22-6 for optimum results.